Utility guidesStep by step
How Does Shams Dubai Approval Work, Step by Step?
DEWA's Shams Dubai process in 3 stages and 6 steps: size limit, review times, export credits, yearly inspection and the connection cap, in plain English.
By Basheer Ansari, Co-Founder & Managing Director
13 min readLast reviewed

The short answer
Shams Dubai is DEWA's programme for connecting rooftop solar to Dubai's grid under net metering. DEWA's process has 3 stages and 6 steps: engage a contractor from DEWA's enrolled list, file the application, get design approval and a fee estimate, request inspection, connect, then generate. Your community's NOC is not a DEWA step, but it often sets the timeline. As of 14 November 2026, DEWA publishes 12 working days for design approval and estimate.
- in DEWA's own process, in 3 stages
- 6 steps
- DEWA's published design review (working days)
- 12 days
- All-in: utility approvals included in our price.
On this page12 sections
- in DEWA's own process, in 3 stages
- 6 steps
- DEWA's published design review (working days)
- 12 days
- All-in: utility approvals included in our price.
What is Shams Dubai?
Shams Dubai is the programme under which DEWA connects rooftop solar to its grid with net metering. It rests on Executive Council Resolution No. (46) of 2014, and DEWA's operative rules are its Connection Conditions, version 4.1, November 2025.
Launched under the Dubai Clean Energy Strategy 2050, Shams Dubai supports DEWA's goal of 100 per cent of Dubai's power production capacity from clean sources by 2050. It lets buildings generate their own solar power while staying connected to DEWA's grid. In a billing cycle where you export more than you import, DEWA bills no consumption charge. The surplus carries forward.
Five ground rules shape everything else:
- Grid-connected villas. In Dubai, villas and businesses connect with net metering: the grid is your storage, so a grid-connected system needs no battery. In Dubai, off-grid is offered for any site, including DEWA-connected ones. An off-grid system runs its own circuits and is never connected to the DEWA grid.
- Enrolled professionals only. DEWA requires an enrolled consultant or contractor for design, installation and verification. See DEWA's list of enrolled companies, last updated 18 July 2025.
- Rooftops and existing structures. DEWA's text says generators 'shall be installed on rooftops, facades and other existing structures. Ground-mounted installations are not envisaged.' The system must sit wholly inside the plot.
- Your own use. Shams Dubai output offsets your own consumption only. DEWA does not accept arrangements where a producer rents out space so tenants can use the power.
- Everything is inspected. DEWA inspects the installation before it connects you.
- Net metering
- A bidirectional meter counts what you import and what you export. Exports are deducted from imports before DEWA applies its tariff slabs.
- Bidirectional meter
- DEWA's 'tariff meter'. DEWA installs it at no extra cost over its normal service charges.
Who is eligible for Shams Dubai?
DEWA's FAQ says solar can go on homes, commercial and industrial premises where site conditions suit. The Resolution applies to any producer with a DEWA consumption account in the emirate, including free zones and DIFC.
- Villa owners: the usual case. A villa with usable roof space and a DEWA account.
- Businesses: offices, warehouses, factories and schools. Above 100 kW, DEWA requires a performance test. Above 400 kW, DEWA says extra grid equipment may be needed, and its cost may be added to the connection.
- Tenants and apartments: see the section below. DEWA states the rules for them directly.
- NOC
- A No-Objection Certificate from your community or developer, issued before installation and paid by the owner.
How does the Shams Dubai process work?
DEWA's connection process has three stages: Stage A, permits and connection application. Stage B, inspection and connection. Stage C, generation. Our steps below follow DEWA's six, with the community NOC added as step 2. Step labels show DEWA's own step number.
Step 1: Feasibility and enrolled contractor (DEWA step 1, Stage A)
- You and the installer
- We aim to send your proposal within a week
A recent DEWA bill and satellite roof review answer most of the feasibility question: how much you consume, when, and what your roof can host. DEWA's first step is to engage an enrolled contractor or consultant. Every system is designed to your utility's current rules: DEWA, SEWA, TAQA or EtihadWE.
Step 2: Community NOC (not a DEWA step)
- Your community
- Timeline set by the community
If your villa sits in a master community, the developer or community issues a No-Objection Certificate before installation. Each community sets its own forms and turnaround, and the owner pays for it. Standalone plots typically skip this step. DEWA's own 'Solar NOC' is a different item, bundled into its single online application.
The community NOC, not DEWA, is usually the step that sets your timeline.
Step 3: Permits and connection application (DEWA step 2, Stage A)
- The installer and DEWA
- Free to apply
The enrolled contractor submits the application through DEWA's online service, Getting Solar Permits & Connections. DEWA lists the service fee as free. The application bundles the Solar NOC, design approval and fee estimate. The reference number starts with S-.
Step 4: Design approval and fee estimate (DEWA step 3, Stage A)
- DEWA
- 12 working days
DEWA reviews the drawings, equipment datasheets and electrical design. It issues a technical design approval and a connection fee estimate. The fee is a one-off DEWA charge, and it is included in the price on your proposal.
Step 5: Installation, then inspection request (DEWA step 4, Stage B)
- The installer
Mounting, panels, inverter, cabling and protection are built to the approved design. Deviations mean re-approval. Installation typically takes 2–4 weeks once we start on site.* When the work is done, the contractor notifies DEWA and files the Solar PV Inspection Application.
*Depends on the project size.
Step 6: Inspection, agreement, meter and connection (DEWA step 5, Stage B)
- DEWA
- Times published by DEWA
DEWA inspects the site, a connection agreement is signed, and DEWA installs its meters and connects you. Systems above 100 kW also need a performance test (3 working days). DEWA's FAQ says an old electromechanical meter is replaced. Your existing meter may already be suitable.
Step 7: Generation and net-metered billing (DEWA step 6, Stage C)
- You and DEWA
- Every bill after connection
Your system generates. Each monthly bill shows exports and credits deducted first, then DEWA's tariff slabs applied to any net import. You also get a monitoring app from the installer.
- DEWA-enrolled contractor
- A contractor registered with DEWA to design and install Shams Dubai systems.
- List of Eligible Equipment
- DEWA's published, non-exhaustive list of panels and inverters. DEWA last updated it on 10 June 2025. Other equipment can pass if it meets DEWA's standards and proof is submitted.
How big a system can I connect under Shams Dubai?
DEWA limits capacity by your plot's Total Connected Load (TCL). TCL is the sum of the approved load on the consumption accounts you hold in the plot. Under clause 2.2 of the Connection Conditions, the total Maximum Capacity of your generators at a plot must not exceed the share the table allows. A plot can never exceed 1,000 kW.
0–100
- Share of TCL in slab
- 100%
- Most the slab adds (kW)
- 100
- Maximum capacity at top of slab (kW)
- 100
100–200
- Share of TCL in slab
- 75%
- Most the slab adds (kW)
- 75
- Maximum capacity at top of slab (kW)
- 175
200–400
- Share of TCL in slab
- 50%
- Most the slab adds (kW)
- 100
- Maximum capacity at top of slab (kW)
- 275
400–600
- Share of TCL in slab
- 25%
- Most the slab adds (kW)
- 50
- Maximum capacity at top of slab (kW)
- 325
Above 600
- Share of TCL in slab
- 5%
- Most the slab adds (kW)
- 675
- Maximum capacity at top of slab (kW)
- 1,000
DEWA may also set a stricter technical limit at your connection point. Public and mobile public EV charging loads are left out of TCL.
For illustration: sizing with the slabs
This is arithmetic on the published table, not a quote or a real project.
- TCL 60 kW: all of it counts, so the limit is 60 kW.
- TCL 240 kW: 100 kW + 75 kW + 50% of the 40 kW above 200 = 195 kW.
- TCL 500 kW: 275 kW at 400 kW, plus 25% of the 100 kW above it = 300 kW.
How do export credits work?
Under clause 2.4 of the Connection Conditions:
- Carry-forward: DEWA carries surplus 'indefinitely from one Billing Cycle to the next, without any limitation of time or quantity'.
- No cash: DEWA will not pay compensation for surplus. Resolution Article 9 says no payment may be made against it.
- Closing the account: if the hosting account closes with a final bill, DEWA forfeits any remaining surplus without payment.
- Sale or rent: the generator can move to a new owner's or tenant's account, but the surplus is not transferred.
- Where it can be used: only against your own accounts in the same plot. Not other people, and not other plots.
- Several accounts: you set the offset order at application. After DEWA approves a change to that order, further changes are locked for 90 days.
- Non-payment: if DEWA disconnects the hosting account, import and export both stop.
- Surplus electricity
- The excess of what you export over what you import in a billing cycle. The cycle is currently monthly.
How long does Shams Dubai take, and what are DEWA's published times?
Feasibility & proposal
- Typical target
- We aim to send your proposal within a week.
Community NOC
- Typical target
- set by your community
DEWA design approval and estimate
- Typical target
- 12 working days
Installation
- Typical target
- Installation typically takes 2–4 weeks once we start on site.*
DEWA inspection
- Typical target
- 1 working day
Performance testing (above 100 kW only)
- Typical target
- 3 working days
Metering
- Typical target
- 1 working day
- Working days
- DEWA's service page counts working days, not calendar days. The times are DEWA's own, checked on 14 November 2026.
What does Shams Dubai cost?
- The system: priced all-in from your bill: the calculator gives an indicative price.
- DEWA's application: DEWA lists the service fee as free.
- DEWA's connection fee: DEWA estimates a one-off connection fee at design approval. It is included in the price on your proposal. DEWA says the fee is lower for systems under 10 kW that waive the generation check meter, and that grid equipment costs may be added above 400 kW.
- Meters: DEWA installs the bidirectional tariff meter at no extra cost over normal service charges. The generation check meter sits inside DEWA's connection fee, which is part of your proposal price.
- Our proposal: The price on your proposal is the price you pay*: utility approvals included. Municipality fees and community NOCs are paid by the owner. *After your site survey.
- Municipality fees
- Fees for the building permit and completion certificate from the competent authority, such as Dubai Municipality, Trakhees or Etihad Esco. The owner pays them, as with the community NOC.
What maintenance and inspection does DEWA require each year?
The owner carries this duty under clause 3.3 of the Connection Conditions:
- Keep a valid maintenance contract with a DEWA-enrolled contractor.
- Have that contractor inspect and service the system at least once every twelve months. DEWA recommends six-monthly.
- Use only an enrolled contractor for critical repairs and replacements.
- Dispose of panels under the waste rules. Keep any renewable energy certificates (I-RECs) for self-redemption.
What is the annual connection cap?
DEWA may impose an Annual Connection Cap on the solar capacity connected in a calendar year (Connection Conditions, clause 4.1). If the cap is reached, DEWA keeps receiving, processing and approving requests. Approved requests are put on hold and connect from the following calendar year, 'first approved, first connected'. As of 14 November 2026 we found no published cap value and no pause on new connections.
Can tenants and apartment owners use Shams Dubai?
Here is what DEWA states, in its FAQ:
- Building owners: DEWA says it does not plan to offset one plant's output against different customers' consumption. An owner can offset only the common areas, such as lighting, air-conditioning and lifts, measured on meters the owner holds.
- Tenants: individual tenants can install solar for their own use, tied to their own accounts.
- Selling or renting: the generator can move to the new owner's or tenant's account. Accumulated credit cannot move.
DEWA's text does not say more than this about apartment roofs or tenant paperwork. Confirm your case with DEWA or your enrolled contractor.
What stalls a Dubai solar project?
- Starting installation before the NOC: communities can and do order removal. Keep to the sequence.
- Equipment that fails DEWA's standards: a bargain inverter that does not meet them fails design review, and you pay twice.
- Undersized paperwork, oversized promises: quotes that ignore NOC drawings and fees look cheaper and finish slower.
- Design-versus-build drift: installing anything different from the approved drawings triggers re-approval at inspection.
- Account mismatch: the DEWA account holder and the property owner must line up in the application.
- Missing maintenance contract: DEWA requires one with a DEWA-enrolled contractor, so budget for it from day one.
Every emirate side by side: rooftop solar rules in each emirate.
Sources
- DEWA Connection Conditions for Generators of Electricity from Solar Energy, V4.1, Nov 2025, checked 14 Nov 2026. Clauses 1.3, 2.1 to 2.5, 3.3, 4.1.
- Executive Council Resolution No. (46) of 2014, checked 14 Nov 2026. Articles 2 and 9.
- DEWA: Shams Dubai connection process, checked 14 Nov 2026. Stages A to C and the six steps.
- DEWA: Apply for Solar Permits & Connections, checked 14 Nov 2026. Service fee and delivery times.
- DEWA: Shams Dubai FAQ, checked 14 Nov 2026. Storage, tenants, building owners, meters.
- DEWA: enrolled consultants and contractors, checked 14 Nov 2026. List updated 18 July 2025.
- DEWA: List of Eligible Equipment, checked 14 Nov 2026. Updated 10 June 2025.
Shams Dubai FAQs
All 48 questions →Your number, from one bill.
Keep reading
- What Are the Rules for Rooftop Solar in Abu Dhabi?What DoE's rooftop solar policy allows in Abu Dhabi as of 14 November 2026: who it covers, self-consumption only, licences, TAQA Distribution and tariffs.
ExplainerUtility guides
8 min readReviewed
- How Does EtihadWE's Rooftop Solar Scheme (DSS) Work?EtihadWE's Distributed Solar Systems rules for Ajman, Umm Al Quwain, Ras Al Khaimah and Fujairah: who can join, size limits, billing, steps and status today.

Step by stepUtility guides
11 min readReviewed
- What Does SEWA Publish About Rooftop Solar in Sharjah?As of 14 November 2026, SEWA publishes no customer rooftop-solar connection or net-metering programme. What that means in Sharjah.
ExplainerUtility guides
4 min readReviewed