What Are the Rooftop Solar Rules in the UAE?
UAE rooftop solar rules as of 14 November 2026: DEWA, EtihadWE, SEWA and Abu Dhabi compared on export treatment and size limits, with a guide for each.
By Basheer Ansari, Co-Founder & Managing Director
8 min readLast reviewed
The short answer
Each emirate's utility sets its own rooftop solar rules. Dubai uses net metering under Shams Dubai. Ajman, Umm Al Quwain, Ras Al Khaimah and Fujairah have EtihadWE's DSS rules. Abu Dhabi allows self-consumption only. Sharjah's SEWA publishes no customer programme. This page compares them as of 14 November 2026 and links one guide for each.
On this page9 sections
Your number, from one bill.
What are the rooftop solar rules in the UAE?
Each emirate's utility sets its own rooftop solar rules. Dubai's DEWA credits surplus power on future bills. EtihadWE has published its Distributed Solar Systems (DSS) rules for the Northern Emirates but lists no application service yet. Abu Dhabi allows self-consumption only, and Sharjah's SEWA publishes no customer programme. All of this is as of 14 November 2026.
- Net metering
- Imports and exports are netted on one bidirectional meter and surplus becomes credit on future bills. In the UAE this is Dubai's Shams Dubai rule.
- Zero-export
- A system sized to your daytime load that sends nothing to the grid.
How do the rules compare from one emirate to the next?
Emirates served
- DEWA
- Dubai
- EtihadWE
- Ajman, Umm Al Quwain, Ras Al Khaimah, Fujairah
- SEWA
- Sharjah
- Abu Dhabi DoE with TAQA Distribution
- Abu Dhabi, with AADC in Al Ain
Grid-connected scheme
- DEWA
- Shams Dubai
- EtihadWE
- Distributed Solar Systems (DSS)
- SEWA
- Not published
- Abu Dhabi DoE with TAQA Distribution
- DoE rooftop solar policy
Export treatment
- DEWA
- Net metering: surplus carried forward as credit on future bills, no cash
- EtihadWE
- All solar exported through a second DSS meter, billed monthly as Net = A − B. Rules published September 2024. No application service listed
- SEWA
- Not published
- Abu Dhabi DoE with TAQA Distribution
- Self-consumption only. No export at this stage
Size limit
- DEWA
- Share of your plot's connected load, up to 1,000 kW per plot
- EtihadWE
- 10% of the connected load, up to 1,000 kW per account
- SEWA
- Not published
- Abu Dhabi DoE with TAQA Distribution
- Not published
Guide
- EtihadWE
- EtihadWE DSS guide
- SEWA
- SEWA guide
- Abu Dhabi DoE with TAQA Distribution
- Abu Dhabi guide
What are the rules in Dubai under Shams Dubai?
DEWA's Shams Dubai programme connects rooftop solar to Dubai's grid under net metering. It rests on Executive Council Resolution No. (46) of 2014, and DEWA's current Connection Conditions are Version 4.1 from November 2025.
Panels go on rooftops, facades or other existing structures, wholly within your plot, and the power offsets only your own DEWA accounts there. When you export more than you import in a billing cycle, DEWA carries the surplus forward to the next cycle with no limit of time or quantity. It pays no cash for surplus, and any surplus left when the account closes is forfeited.
DEWA sets the size by your plot's Total Connected Load: 100% of the first 100 kW, lower shares for each further slab, and never more than 1,000 kW per plot. Only DEWA-enrolled contractors and consultants can submit the application.
Read the full process in our Shams Dubai guide.
What are the rules for Ajman, Umm Al Quwain, Ras Al Khaimah and Fujairah?
EtihadWE supplies these four emirates. With the Ministry of Energy and Infrastructure, it announced its Distributed Solar Systems (DSS) scheme on 22 September 2024 and published the rules in two Version 1 documents.
Under the DSS, all the power your panels make goes through a second meter. Each month EtihadWE bills the difference: Net = A − B. A DSS may be up to 10% of your account's connected load and never more than 1,000 kW, on rooftops only. Phase 1 covers Residential Local, Industrial and Agricultural accounts. Industrial accounts on a preferential discounted EtihadWE tariff are not included.
As of 14 November 2026, EtihadWE lists no approved-contractor list, application service or fee schedule for the DSS. Systems in these emirates are installed zero-export today, with hybrid (battery) and off-grid options.
Read the clause-by-clause breakdown in our EtihadWE DSS guide.
What are the rules in Abu Dhabi and Al Ain?
Abu Dhabi's Department of Energy (DoE) runs a rooftop solar policy, effective 5 February 2026. It is for self-consumption. DoE says net metering and energy exports are not permitted at this stage.
The policy covers any customer, a person or a company, supplied under TAQA's current tariffs. Phase 1 started with farms, rest houses and ranches. Phase 2, announced on 31 March 2026, extends the policy to villa owners and residential buildings where applicable. DoE assesses large consumers case by case. The policy says DoE will issue detailed guidelines on metering, settlement and applications. We have not found them, and we found no published size limit for homes.
Customers deal with TAQA Distribution, and AADC serves Al Ain city. Confirm which one covers your meter.
Read more in our Abu Dhabi guide.
What are the rules in Sharjah?
As of 14 November 2026, SEWA publishes no customer rooftop-solar connection or net-metering programme on its website or its e-services portal. We found no application service, size cap or fee for solar there.
Two things are easy to mistake for a customer programme. SEWA's 60 MW Sana solar plant, opened on 25 June 2025, is a utility project. Sharjah Sustainable City's net metering, reported in 2022, is run by the developer for that community.
SEWA's customer line is 600 566 665 if you want its current position.
Read more in our Sharjah guide.
Which system types are available in each emirate?
In every emirate, systems are designed to each site's needs: zero-export, hybrid (battery) or off-grid.
In Dubai, DEWA credits your surplus on future bills, so a grid-connected system needs no battery. In Dubai, off-grid is offered for any site, including DEWA-connected ones. An off-grid system runs its own circuits and is never connected to the DEWA grid.
For battery choices, see our guide to solar batteries.
How much can I save in each emirate?
Tariffs differ by utility, so savings do too. Our guide to solar costs by emirate shows them for each one. For pages on the areas we cover, see locations.
Sources
- DEWA, Shams Dubai connection process, checked 14 Nov 2026
- DEWA, Connection Conditions V4.1, November 2025, checked 14 Nov 2026: sections 2.1, 2.2 and 2.4
- EtihadWE, DSS announcement, 22 September 2024, checked 14 Nov 2026
- EtihadWE, DSS Connection Conditions, Version 1, checked 14 Nov 2026
- Abu Dhabi DoE, PV and Battery Energy Storage Systems for Self Supply Policy, effective 5 February 2026, checked 14 Nov 2026: sections 2 and 2.1
- Abu Dhabi DoE, phase two announcement, 31 March 2026, checked 14 Nov 2026
- WAM, Abu Dhabi DoE launches its rooftop solar policy, 5 February 2026, checked 14 Nov 2026: phase 1 scope
- Gulf News, Abu Dhabi expands the solar policy to residents, March 2026, checked 14 Nov 2026: commercial and industrial invitation
- TAQA Distribution, residential overview, checked 14 Nov 2026
- SEWA, electricity, checked 14 Nov 2026
- SEWA, e-services portal, checked 14 Nov 2026
- Khaleej Times, Sana solar plant, checked 14 Nov 2026
- The National, Sharjah Sustainable City, 2022, checked 14 Nov 2026
UAE solar rules FAQs
All 48 questions →Your number, from one bill.
Keep reading
- What Are the Rules for Rooftop Solar in Abu Dhabi?What DoE's rooftop solar policy allows in Abu Dhabi as of 14 November 2026: who it covers, self-consumption only, licences, TAQA Distribution and tariffs.
ExplainerApprovals and rules
8 min readReviewed
- How Does EtihadWE's Rooftop Solar Scheme (DSS) Work?EtihadWE's Distributed Solar Systems rules for Ajman, Umm Al Quwain, Ras Al Khaimah and Fujairah: who can join, size limits, billing, steps and status today.

Step by stepApprovals and rules
11 min readReviewed
- How Does Shams Dubai Approval Work, Step by Step?DEWA's Shams Dubai process in 3 stages and 6 steps: size limit, review times, export credits, yearly inspection and the connection cap, in plain English.

Step by stepApprovals and rules
13 min readReviewed